Description : Steel Bridge supervision Service for Kazakhstan Almaty Highway Construction Project(work section#3)
Bridge Name : Almaty Highway Bridge
Owner : Kazakhstan Highway Corp.
Client : Dongsung Engineering Co., Ltd
Prime Vendor : Kurgan Steel/Russia
Remarks :

Project Name: Steel Bridge supervision for Kazakhstan Almaty Highway Construction Project(work section#3)

Manufacturer: Kurgan Steel/Russia

Duration: Mar. 2015~Oct. 2015

Main Features:
Total steel weight 3,220Ton Orthotropics steel deck, length of bridge L=683m, 9 spans, Erection method: ILM

 
 
Description : Third Party Inspection Service for Walterdale Bridge Replacement Project during manufacturing
Bridge Name : Walterdale Bridge, Canada
Owner : City of Edmonton, Canada/ Acciona Pacer J/V
Client : Hyundai Engineering & Steel Insustries Co., Ltd.
Prime Vendor : Hyundai Engineering & Steel Insustries Co., Ltd.(Yulchon Factory)
Remarks : 1) Project Name: Third Party Inspection Service for Walterdale Bridge Replacement Project during manufacturing. 2) Main Particulars : Replacement of existed 3 span truss type Bridge to Nielsen Archbridge(14 degree to the vertical), W 20.4m x total span 230m, Total steel weight 5,213Ton, 3)Period of inspection service : April 2014 ~ April 2015 (12 Months) 4) Hyundai Engineering & Steel Insustries Co., Ltd.(Yulchon Factory), Suncheon, Korea 5) Purchaser/ Constructor : City of Edmonton(Canada)/ Acciona Pacer Joint Venture
 
 
Description : Supervision Service of Prestressing Strand for Turkey Northern Marmara Motorway Project During Manufacturing
Bridge Name : Bosphorus Bridge
Owner : ICA (Ictas/Turkey+ Astaldi/Italy Joint Venture)
Client : ICA
Prime Vendor : KISWIRE(Yangsan, Korea) & WISCO (Long Teng Steel in China)
Remarks :
• Project Name : Supervision Service of Prestressing Strand for Turkey Northern Marmara Motorway Project  During Manufacturing.

 • Service Duration : 
Jan. 2014  ~  Feb. 2015

• Purchaser: ICA (Ictas/Turkey+ Astaldi/Italy Joint Venture)

• Constructor :
IC Ictas-Astaldi JV

• Manufacturer : KISWIRE(Yangsan, Korea) & WISCO (Long Teng Steel in China) 
 


• Inspection Article & Inspection Items:

  1)   Article : Prestressing Strand

  2)   Gross Weight : 18,000 ton(3000Ton  KISWIRE, 15000Ton  WISCO, China) 

  3)   Main Spec.

            • 
Material : ASTM A 416 Type 270K Low Relaxation

   
•  PPWS cables

























Nominal

Diameter

(mm)


Cross

Sectional Area

(mm2)


Unit Weight

(Kgf)


Yield

Strength

(Kgf)


Strand Breaking

Strength

(Kgf)


Elongation

(%)


Remark


15.24


140.0


1.102


23,460


26,070


Min.3.5


 


•  Relaxation Loss

-  Under loading of 70% load of Breaking Strength : Max. 2.5%

-  Under loading of 80% load of Breaking Strength : Max. 3.5%

•  Straightness Inspection

•  Appreance Inspection

 


 
 